C O N S T R U C T I V E T A L K
2 0 2 0 V O L . V I
I S S U E I I P A G E 3
not enough and further investigation was required to ascertain the existence or
absence of suspected defects. Id. at 232. The appellate court reversed the trial
court’s dismissal and held the engineering report did not conclusively establish
the defects were patent. Id.
When Will the Court Infer an Owner Had Notice of a Latent Defect?
In Florida, “where there is an obvious manifestation of a defect, notice
will be inferred at the time of manifestation regardless of whether the plaintiff
has knowledge of the exact nature of the defect.” Hochberg v. Thomas Carter
Painting, Inc., 63 So. 3d 861, 862 (Fla. 3d DCA 2011). In Hochberg, on their
first night in their newly constructed home, the owners recognized the over-
whelming smell of mold, triggering an allergic reaction in the wife. 63 So. 3d at
862. In November 2003, the owners hired an engineer to evaluate the issue and
the engineer found significant issues with the construction of the house. Id. In
July 2008, the owners sued the construction team for negligent work and argued
the statute of limitations should not have tolled until they knew that it was the
negligence of the subcontractors that caused the defects. Id. at 863. The trial
court held the statute of limitations began running when the owners discovered
the manifestation of the defects and did not begin running when the owners dis-
covered the subcontractors were responsible for the defective construction. Id.
The appellate court affirmed. Id.
The statute of limitations begins to run once a latent defect is discovered,
not once the cause of the defect is known. Havatampa Corp. v. McElvy, Jenne-
wein, Stefany & Howard, Architects/Planners, Inc., 417 So. 2d 703, 704 (Fla. 2d
DCA 1982). In Havatampa, ever since plaintiff took possession of the building
from the construction team in April 1972, the roof leaked. Id. In April 1976, four
years after moving in, plaintiff hired a consultant to assess the roof. Id. The con-
sultant determined the cause of the leak was very complex and that it was not
reasonably possible for the owner to have known the full extent of the specific
nature of the defects that caused the leaks. Id. In August 1976, the owner sued
the designer and construction team for the roofing leaks. Id. The trial court held
that the owner’s claim was time barred because the four-year statute of limita-
tions began to toll when the plaintiff learned of the roof leak, upon taking pos-
session of the building, and not when the plaintiff knew what caused the defect.
Id. The appellate court affirmed the trial court’s holding that plaintiff’s action
was time barred, noting “plaintiff cannot rely on a lack of knowledge of the spe-
cific cause of the problem to protect it against expiration of the four year statute
of limitations.” Id. Similarly, in Almand Const. Co., the owners discovered their
home was settling and causing structural damage. Almand Const. Co., Inc. v. Ev-
ans, 547 So. 2d 626, 627 (Fla. 1989). Plaintiffs later retained an engineer that
opined the unsuitable and defective fill used caused the structural damage. Id.
The court held the owner’s knowledge of the settling and structural damage trig-
gered the statute of limitations to run. Id. The engineer’s report about the unsuit-
able fill did not trigger the four-year statute of limitations since the owners were
already on notice that their home was settling. Id.
However, notice is not inferred simply because there is a leak in a building.
When the manifestation of the defect is not obvious and could be due to causes
other than an actionable defect, the court will not infer the plaintiff had
(Connued on page 4)
(Continued from page 2)