110
Evaluation
Alternative 2: 230kV Resiliency and Redundancy
Alternative 3: 69kV/138kV Repair/Resiliency
Damaged infrastructure that would
require more frequent emergency
repairs could result in long-term,
minor to moderate, temporary or
permanent, indirect, adverse impacts
on biological resources, such as
disturbances of birds, other wildlife,
and protected species from the
generation of noise and the presence
of people and machinery, or the
spread of invasive species.
Construction could result in short-term, temporary, negligible impacts on habitats including an estimated 452 acres of
wetlands (based on NWI data).
Long-term negligible to minor, permanent impacts on habitats could occur in estimated 0.4 acres where the
transmission line pole bases will be installed, 2.4 acres in wetlands where substations will be constructed or
expanded, and in 1.5 acres where the permanent footprints of the three waterway crossings permanent workspaces
(GIWW, CSC, and Mermentau River) intersect wetland habitats.
Construction could result in short-term, temporary, negligible to minor impacts on estuarine emergent marsh,
estuarine open water, and estuarine mud bottom EFH habitats, such as avoidance, accidental crushing, and siltation
,
which would be minimized using the BMPs in Appendix A Areas of temporary impact would be restored to pre-
construction conditions and monitored in coordination with NOAA to confirm recovery.
Long-term, permanent impacts on estuarine emergent marsh (estimated at less than 2.5 acres) and estuarine open
water/mud bottom (estimated at less than 0.7 acres) EFH could occur where permanent components of waterway
crossing infrastructure and substations are installed, although the majority of the work would be conducted in
previously disturbed areas.
JDEC will develop an EFH Assessment and participate in consultation with NMFS for projects conducted under this
alternative that could adversely affect EFH, and will develop a plan with NMFS to avoid, minimize, mitigate, or
otherwise offset adverse effects on EFH.
Construction work could result in short-term, temporary, negligible to minor impacts from disturbance of birds, other
wildlife, and protected species from the generation of noise. FEMA and JDEC will coordinate with NOAA to
evaluate cumulative noise exposure, the radius of potentially injurious levels and behavioral impact levels, species
that may be affected, and whether mitigation strategies will be required to reduce the impact.
Construction work could also result in short-term, temporary, negligible to minor impacts related the presence of
people and machinery. Bird abatement BMPs would be implemented, as necessary, and any temporal restrictions
provided by USFWS or LDWF would be followed. Per LDWF requirements, if work will occur during the nesting
season, a nesting shorebird field assessment would be conducted within two weeks of the beginning of the project.
No long-term impacts on birds and other wildlife are anticipated.
Because HDD under the GIWW, CSC, and Mermentau River could potentially cause short-term, temporary effects on
ESA-listed species under NMFS purview, ESA Section 7 consultation would need to be carried out once the
construction details and project timing have been determined.
Construction is not likely to adversely affect piping plover or red knot and would have no effect on red-cockaded
woodpecker or the four sea turtle species. Construction could occur in suitable Eastern black rail habitat and cause
short-term, temporary, negligible to minor effects. FEMA will consult with USFWS on any projects under this
alternative that have the potential to adversely affect Eastern black rail and employ avoidance and minimization
measures in accordance with Section 7 of the ESA.
This alternative could result in negligible to minor, permanent, adverse impacts from the spread of invasive
vegetation, Roseau scale, and Asian clam as a result of the movement of construction equipment and boats that could
spread seeds, plant material, or organisms, which would be mitigated using BMPs.
In contrast to Alternative 3, this Preferred Alternative would eliminate the need to rebuild the approximately 27.5-
mile 138kV line which spanned wetland habitat and was not along a roadway, thereby providing a benefit to
biological resources by not resulting in temporary or permanent impacts in this area.
Similar short- and long-term impacts on biological
resources as Alternative 2, and follow the same agency
coordination steps and BMPs, however:
• Transmission lines would be placed along the pre-
storm path of the 69kV and the 138kV transmission
lines, with narrower workspace corridors than
Alternative 2 as described in Section 4 but would
require reconstruction of the 27.5-mile 138kV line,
which ran through wetland habitat.
• Short-term, temporary impacts on wetlands are
estimated at 211 acres.
• Long-term, permanent impacts on habitats could
occur in the estimated 0.24 acres where transmission
line pole bases will be installed and in the less than
2 acres where the permanent footprints of the two
waterway crossings at the GIWW intersect wetland
habitats.