What GAO Found
United States Government Accountability Office
Why GAO Did This Study
Highlights
Accountability Integrity Reliability
September 2009
DCAA AUDITS
Widespread Problems with Audit Quality Require
Significant Reform
Highlights of GAO-09-468, a report to the
Committee on Homeland Security and
Governmental Affairs, U.S. Senate
The Defense Contract Audit
Agency (DCAA) under the
Department of Defense (DOD)
Comptroller plays a critical role in
contractor oversight by providing
auditing, accounting, and financial
advisory services in connection
with DOD and other federal agency
contracts and subcontracts.
Last year, GAO found numerous
problems with DCAA audit quality
at three locations in California,
including the failure to meet
professional auditing standards.
This report addresses audit quality
issues at DCAA offices nationwide.
GAO was asked to (1) conduct a
broad assessment of DCAA’s
management environment and
audit quality assurance structure,
(2) evaluate DCAA actions to date
to correct previously identified
problems, and (3) identify potential
legislative and other actions for
improving DCAA effectiveness and
independence. To achieve these
objectives, GAO analyzed DCAA’s
mission, strategic plan, audit
policies, and quality assurance
program; conducted interviews;
reviewed selected audits at DCAA
offices; and analyzed legislative
and other actions.
What GAO Recommends
GAO makes 17 recommendations
to DOD and the DOD Inspector
General (IG) to improve DCAA’s
management environment, audit
quality, and oversight. GAO also
discusses matters that Congress
should consider to enhance the
effectiveness and independence of
DCAA contract audits. DOD and
DOD IG generally agreed with
GAO’s recommendations,
concurring with all but two.
GAO found audit quality problems at DCAA offices nationwide, including
compromise of auditor independence, insufficient audit testing, and
inadequate planning and supervision. GAO’s conclusions stem from a review
of 69 audit assignments supporting contract award and administrative
decisions; an assessment of DCAA’s audit quality assurance structure, which
found similar audit quality problems but gave satisfactory ratings to deficient
audits; and DCAA’s rescission of 80 problem audit reports. The rescinded
audits supported decisions on pricing and contract awards and impacted the
planning and reliability of hundreds of other DCAA audits, representing
billions of dollars in DOD expenditures. GAO findings include the following.
Selected Details of Audits GAO Reviewed
Contractor Audit Significant case study issues
Research and
development
grantee
Billing
system
• DCAA auditors spent 530 hours to support an audit of a
nonexistent billing system and reported adequate system controls.
• Instead, DCAA should have relied on the Single Audit Act report on
the grantee’s cash management system. DCAA agrees.
Combat
systems
Billing
system
• This was a new system and therefore high risk, but auditors
deleted key audit steps related to contractor policies and internal
controls over progress payments without explanation.
• One auditor told GAO he did not perform detailed tests because
“the contractor would not appreciate it.”
• DCAA allowed the contractor 7 months to address 6 significant
deficiencies, dropping 2 and downgrading the other 4.
• DCAA rescinded this audit report following GAO’s review.
Iraq
reconstruction
Accounting
system
• Contractor objected to draft report, which included 8 significant
deficiencies in the accounting system.
• Auditors dropped 5 significant deficiencies and downgraded 3
others to suggestions to improve without performing new work.
• Supervisory auditors directed audit staff to delete some audit
documents, generate others, and in one case, copy the signature
of a prior supervisor onto new documents making it appear that the
prior supervisor had approved a revised risk assessment.
• Supervisory auditor who approved altered documents was later
promoted to western region quality assurance manager, where he
served as quality control check over thousands of audits.
Source: GAO.
GAO found DCAA’s management environment and quality assurance structure
were based on a production-oriented mission that put DCAA in the role of
facilitating DOD contracting without also protecting the public interest. DCAA
has taken several positive steps. However, DOD and DCAA have not yet
addressed fundamental weaknesses in DCAA’s mission, strategic plan,
metrics, audit approach, and human capital practices that had a detrimental
effect on audit quality.
To improve DCAA oversight, the DOD Comptroller requested Defense
Business Board and “tiger team” reviews and established a DCAA Oversight
Committee. In addition, in the short-term, Congress could provide DCAA with
certain legislative protections and authorities similar to those available to IGs.
In the longer term, Congress may wish to consider organizational changes to
elevate DCAA to a component agency reporting to the Deputy Secretary or to
establish an independent governmentwide contract audit agency.
View GAO-09-468 or key components.
For more information, contact Gregory Kutz at
(202) 512-6722 or kutzg@gao.gov.