\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
1
Case study written commentary examples
Introduction
The following are five examples of sections of recent case studies submitted for Experience
Area D - Procurement. They are all from applicants who were successful in gaining
registration. Their co-operation in making these examples available to prospective
registrants is much appreciated.
They have been edited only to remove critical details that may have allowed readers to
identify the architect, their practice, the client or the project. All other material is the
applicants own work including formatting. Any errors, omissions, inaccuracies and
inconsistencies remain.
The Board offers these examples for information only to provide an indication of the range of
work submitted by applicants who have met the minimum standard in their assessment. The
Board specifically does not vouch for the completeness, accuracy, or appropriateness of
these case study examples.
Remember that the prepared case studies provide background on which to structure the
assessment conversation and are not assessed in their own right.
The assessors are not expecting comprehensive theses on the Experience Areas, brevity is
a virtue.
It may be of interest to graduates commencing the preparation of case studies to know that
the total word count of these five applicants’ examples (Experience Area D only and
excluding appendix materials) ranged from under 1000 words to over 5000 words. These
applicants’ total word counts for all their commentaries varied from just over 9000 words to
more than 29,000 words.
Issued 2 February 2011
\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
2
Example 1
1. Outcome (NZRAB)
To establish an appropriate procurement method and complete contractual arrangements with all participants.
2. Overview
Different types of projects and clients needs can lead to several options of project delivery strategies.
These should ideally have been agreed upon at an early stage between Architects and clients. Whatever
strategy has been chosen, there will be a time at which a contractor needs to be appointed. A procurement
method has to be chosen to ensure that the contractor appointed to the job would guarantee the project is
carried out in an efficacious manner and is of an appropriate standard of quality. These matters can be
considered of different weight for different clients; there could be projects giving priority to the time
aspects, others to quality, others to budget, another to a combination of those. To meet Client’s need it is
fundamental that the right project delivery strategy and procurement method be chosen.
Once the strategy has been agreed upon, Architects can have different roles, assisting clients and/or the
Project Manager as a consultant or administrator.
A tender process will be in place unless the contract will be negotiated with a specific contractor. The
tender will need to be administrated by the Architect, the Project Manager or others. The Administrator of
the tender process is the administrator appointed in the contract, and s/he needs to guarantee fairness
towards all people involved in the process, including the client and builders.
3. Performance Indicators
Knowledge and familiarity of different types of contracts and contract
conditions has been demonstrated.
The procurement method for the main contract was an invited tender. This was due to the size of the job
and the need for the contract works to be ended in the time assigned.
The contract used had been NZS 3910:2003 with amendments as stated in Conditions of Tender and
Condition of Contract.
(ref. D1 p. 114-124 - selection of Condition of Tender for the Main Contract).
This Contract, differing from NZIA SCC did not require the administrator to be an Architect. The
administrator of the contract, defined as Engineer had been appointed the Project Manager. Engineer to
the contract administrated with architect consultancy.
Experience and knowledge of the role of the Architect in preparing
documentation has been demonstrated.
The Project Manager had administrated the tender and the entire contract thereafter. The Architect
dealt directly with the PM in providing technical consultancy and the documents needed. As other
consultants were engaged from the Architects, we coordinated the sub-consultants in order to deliver
consistent and accurate sets of documents to the PM for use as tender documents and during tender process,
e.g. specifications, notice to tenderers etc.
(ref. D2 p. 125-127 - communication Project Manager/Architect + Architect CI for refurbishment tender
attached).
(ref. D3 p. 128 - Notice to Tenderer, demolition contract).
(ref. D4 p. 129-140 - selection of drawings issued for tender / D5 p. / - selection of specifications issued
for tender).
Familiarity with a range of procurement processes has been demonstrated.
\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
3
The procurement process for another commercial project carried out by the practice, can outline some
important issues related to different procurement processes. The project of the ABC Building saw the
Applicant closely involved during the design and documentation stages. Due to the complexity and highly
specific performance requirements of the double skin facade, during the development design stage, it had
been decided to appoint a contractor for this specific work on the base of Design/Build deliver strategy. The
tender had been processed on the base of P&G specification. The DEF project, did not require works of a
high level of specialization, hence it had been tendered on a completed set of detailed drawings and
specifications. Tenderers submitted a fix lump sum price for Preliminary and General plus margin,
subcontractors had been appointed with further tender processes during construction. The Architect
consulted the Project Manager in reviewing tender offers for the Main Contract and instructing the
Contractor about the trade tenderers.
(ref. D6 p. 141 - communication Project Manager/Architect)
(ref. D7 p. 142-152 - selection from tender offer)
(ref. D8 p. 153-161 - selection from tender offer
Appropriate procedures through the tendering and contract negotiation processes
have been followed particularly with respect to ethical principles.
In tender processes in which the Architect is appointed as the administrator of the Contract, ethical
principles are to be followed in respect of the client, builders and colleagues. In this project, the
administrator appointed was the Project Manager, hence the Architect assisted the Project Manager in the
process, still working with respect to ethical principles but within the constraints of a consultancy contract.
4. Conclusion
The tender process had been an important experience for the Applicant as it gave him the opportunity
to get involved in reasonably complex processes due to the large scale of the project and implications of
this.
Several tender processes had taken place in the DEF project, from the demolition through to the
refurbishment, to the Main Contract. These have given the applicant a wide range of experiences with
varying levels of involvement.
The Project Manager driven procurement method of this scale required significant coordination
responsibility regarding the work of sub consultants and on the overall accuracy of the documents
delivered.
The Applicant recognized that the Architects had been working following ethical and professional
principles, ensuring the best interest of the client, providing accurate documents and consulting the Project
Management Team in order to be fair towards the tenderers.
5. Complementary jobs
Below is a selection of jobs in which the applicant has been involved during Procurement stage in the
past three years in New Zealand:
\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
4
Example 2
D1 Procurement Method
At a pre-tender client meeting, in which I participated, it was decided that the contract would be procured by means of a selected
tender process and would be a lump sum contract. It was believed that this process would achieve the best price while minimising
risk to the client.
It was decided that four construction companies would be asked to express interest in submitting a tender for the project. All four
companies selected had previous experience working with either our practice or the client, which ensured confidence that all
were capable of competently completing the project. I wrote to the four selected companies formally inviting them to register
their interest in tendering for the project. As expected, particularly due to the state of the construction industry at the time, all
four companies positively responded, expressing interest in submitting a tender.
[See Appendix D1: Pre-Tender Client Meeting Minutes]
[See Appendix D2: Invitation to Register Interest in Tendering, and Contractor Response]
D2 Conditions of contract
The director-in-charge and I put fourth our intention and confirmed with the client that our practice would be administering the
contract under NZIA Standard Conditions of Contract (SCC) 2007. We explained that these conditions were tailored to be used
specifically by architects, and provided a standard copy of SCC 2007 to the client for review and reference purposes.
D3 Specific and Special Conditions of Contract
The director-in-charge customised the Specific and Special Conditions of Tender (schedules T1 and T2), and the Specific and
Special Conditions of Contract (schedules B1 and B2) of SCC 2007, to be project specific and discussed these with me to ensure I
understood and agreed with the customised details. We then confirmed these with the client who requested that additional items
be included in the Special Conditions of Contract.
The Specific Conditions of Tender outlined (among other details) contract details, architect’s details, the due date for submission
of tenders, and the required tender validity date. We decided to set a tender validity period of 2 months due to the tender
submissions being required just prior to the Christmas period. At any other time of the year, we would have instructed a tender
validity period of 1 month.
The Special Conditions of Tender requested details the tenderers were to include with their tender submission. These included:
Details of margins to be applied to Variations to the Contract
Key Personnel details
Details of a proposed early completion
Labour, Plant and Equipment Dayworks Rates
A Tenderer’s Questionnaire requesting company details
We included a provisional allowance to cover potential unforeseen structural implications associated with the boundary work We
took care to convey the provisional allowance as being for a precise section of work.
Under the Specific Conditions of Contract we included:
Details of the Principal and NZIA Practice
Set a Contractor’s performance bond required of 5% of the contract price
Details of Insurance requirements (due to having an existing building on the site the Principal insured the
contract works)
Site possession date
Practical Completion date
A Defects Liability Period of 6 months
Details of Retentions
Details of Liquidated damages
The time after Practical Completion for submission of the final claim
\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
5
Under the Special Conditions of contract we added a clause outlining additional information required by the contractor in order to
qualify for Practical Completion. The intention of this was to encourage the contractor to provide information such as warranties,
operation and maintenance manuals, and apply for Code Compliance in a timely manner.
At the request of the client we also added a clause stating that “
no additional payments due to extensions of time in respect of
adverse weather will be considered
”.
[See Appendix D3: Special Conditions of Tender]
D4 Tender Collection
After compiling the tender documents, including those of the consultants, I advised the tenderers of when the documents would be
available for collection. An accompanying letter outlined the contents of the tender package. Upon collection, I ensured each
tenderer sign a collection register for record purposes. Each tenderer signed an individual page so that they would not
immediately discover the identities of the other tenderers. It is a policy of our practice not to disclose the identity of the other
tenderers to reduce any change of price exchanging which may disadvantage the principal.
[See Appendix D4: Consultant Correspondence]
[See Appendix D5: Advice to Tenderer of Tender Document Collection Time]
[See Appendix D6: Tender Documentation Issue Letter]
[See Appendix D7: Tender Document Collection Register]
D5 Notices To Tenderers
Several items arose throughout the tender process that necessitated the issue of Notices to Tenderers (NTT). These arose
through queries from tenderers and from conditions of the building consent approved during the tendering period.
One such matter arose when one of the tenderers brought to our attention that the profiled metal roofing system we had
specified was very expensive. Upon review we opted to change this specification.
I sent the Notices to Tenderers out simultaneous to each of the four tenderers, ensuring each received the same information at
the same time and thus no unfair advantage could be gained.
[See Appendix D8: Notice to Tenderers No. 02]
D6 Tender Submission
All tenders were received in the last few hours prior to the tender submission deadline. These were in the form of email, facsimile
and hard copy format. The tenders submitted in the form of email or facsimile were followed up with hard copies.
All tenders received included numerous qualifications, clarifications or conditions.
[See Appendix D9: Tender Submission]
D7 Tender Evaluation
I forwarded all tenders to the client and explained that there were numerous clarifications to work through that could have a
considerable affect to the initial tendered prices.
I set up a spreadsheet that enabled me to enter details of the tenders so that they could be easily compared. The spreadsheet
presented values of each trade, contractor’s margin and the highest and lowest prices of each trade. It also presented details of
margins on variations and indicated the extent of company details provided. I treated this as a live document and updated it as
responses to clarifications were received.
[See Appendix D10: Tender Analysis Spreadsheet]
I requested that the lowest three tenderers remove their clarifications (
tags
) to enable us to evaluate them properly. We chose
not to pursue clarification of the highest tender due to the extent of the price difference between that tender and the next lowest.
In order to remove the majority of the tender clarifications I was required to correspond up to three times with each of the
tenderers. I had some difficultly in receiving responses within the requested timeframes due to the proximity to the Christmas
period. The tender evaluation period extended over three weeks. At another time of year I would have expected the evaluation to
be completed more rapidly. I conveyed this issue to the client who accepted that there may be some delay before we could
confidently recommend a tender to accept.
Interestingly, removing the tender clarifications resulted in very little change to the submitted prices. I credit this to the
competitiveness of the construction industry due to low work volume at that time.
Once all clarifications were removed to our satisfaction, I compiled a tender report to present to the client. The report
summarised the tenders received, highlighted key points of these tenders, and recommended a tender to accept. It also included
\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
6
all correspondence between our practice and the tenderers during the evaluation period. I met with the client together with the
director-in-charge to discuss the report and our recommendation. The client agreed to accept our recommendation. This was the
lowest tender which was submitted by ABC Construction.
[See Appendix D11: Tender Report]
D8 Tender Acceptance
I requested the client confirm the accepted tender via email, for record purposes, before sending a Tender Acceptance letter to
ABC Construction and thus awarding the contract. As soon as this letter was sent, a contract was in place.
The tender acceptance letter also provided details of the other tenders received and asked that the construction programme,
insurances and health and safety plan be prepared.
See Appendix D12: Tender Acceptance Letter]
I received a phone call from ABC Construction immediately after issuing the tender acceptance letter. After learning the other
tendered sums ABC Construction were concerned (unnecessarily) that they had made a mistake despite having been asked to
check their calculations during the evaluation period.
I advised the unsuccessful tenderers in writing.
\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
7
Example 3
Section D – Procurement
Outcomes:
Establish an appropriate procurement method and complete contractual arrangements with all
participants.
Performance Indicators:
Knowledge and familiarity of different types of contracts and contract conditions
demonstrated.
Experience and knowledge of the role of architect in the preparing of documentation has
been demonstrated.
Familiarity with a range of procurement processes has been demonstrated.
Appropriate procedures through the tendering and contract negotiation processed have
been followed particularly with respect to ethical principles.
\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
8
1 Types of procurement
1.1 Negotiated Tender
A Negotiated Tender was chosen as the procurement for this project and is when one contractor is
selected and is asked to submit a tender. This form of procurement allows for negotiation between
the Contractor and the Principal for the price and scope of the contract and this was the
procurement method used for this case study. When selecting a contractor to negotiate with, our
practice will look at the scope, location of the project and if a contractor our practice has used
before would be suitable. Our practice will also discuss with other NZIA practices for feedback on
particular contractors.
Our practice proposes this method with Clients when the project is small in nature or when it might
be hard to secure the selected number of tenderers to tender for the project. I found during the
construction boom up to 2009 that it was hard to get contractors to tender. There was plenty of
work on and there was little in the way of competition between builders. This is the reason why this
procurement method was chosen for this project.
Other forms of procurement:
1.2 Invited/selected tender
A number of tenderers will be pre–selected, contacted and asked to submit a tender. Our practice
will select 3-4 tenderers to tender and up to six tenders is considered sufficient to be competitive.
When I am selecting tenderers, I consult with the Client to see if they have contractor they wish to
use, I then establish a short list of contractors that would be suitable. This is based on my
experience, other staff experience and our practice has a contractor list that shows lists the
contractors the practice has worked with, the type of project and any notes of importance. Other
sources to select suitable contractors would be other Architects and NZIA practices and ask for
recommendations.
An alternative is that an advertisement can invite registrations of interest and submission of
credentials and from there a shortlist can be assembled
1
.
Once a shortlist has been assembled I then ring each suitable tenderer, brief them on the basics of
the project type of work, timeframe to start construction and timeframe to tender, I tend to only
briefly cover any information about the Principal. If they confirm that they wish to tender, I will
confirm in writing the above information and the Principals name.
I advise the Principal of the selected tenderers in writing.
1.3 Open Tender
An open tender is when an invitation to Tender is by a public advertisement. The tenderer has to
supply adequate information to the architect to establish that they are capable of carrying out the
work if successful. This is rarely used nowadays and a tender deposit should be provided for in the
tender documents
2
.
1
NZIA Practice Note PN9.301
2
NZIA Practice Note PN9.301
\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
9
2 Types of tender
2.1 Lump sum
Tenderers are asked to submit a fixed price to carry out the project and this type of tender used for
this case study. This lump sum is based on the documentation supplied at the time of tender.
Compared to rates and margin there is lower risk to the Client in that the price is fixed subject to any
variations.
The disadvantage is that the tenderers will include contingencies for items that they might not have
allowed for during the tender and the price may not be a competitive as rates and margins.
2.2 Guaranteed maximum price
This is when the maximum price of project is fixed at the completion of sketch or developed design
stages. The contractor will vary the work to maintain the program and price and carries all the risk.
The advantages of this for the Client is since the price is fixed there is no risk to cost increase. The
primary disadvantage to the Client is that the Contractor can lower the quality in order to keep
within the agreed price.
Sketch plans and outline specifications need to be thorough or issues can arise if the contractor
claims additional costs for items that they believe could not be anticipated based on the
documentation supplied.
2.3 Rates and margins
The selected tenderers submit a breakdown of Preliminary and General costs, hourly labour rates,
margins on variations and materials. The tenderers are then evaluated on these rates and margins.
This option carries more risk for the Client as there is no fixed price and relies on goodwill between
the parties involved. The advantage to the Client is that the costs are only for items that are used
onsite.
I have used this before on a project where we selected the Contractor at the start of the developed
design stage on the above criteria. Two tenderers were supplied with basic drawings (site plan, floor
plan, typical section and elevation) and an outline specification.
A variation of this is when the tenderer is asked to submit a fixed price. It is then negotiated that the
contract be carried out with labour and carpentry (and sometimes sub-contractors) on a rates and
margins basis. I am working on new house project where this is the system being used.
2.4 Labour Only
A labour only contract is when the Contractor is contracted only to provide labour. All material and
organization of sub trades are organised by the Principal. This creates significant work for the
Principal and has liability issues for who is responsible for the work.
3 Procurement Process
For this case study, our director and I met with the Clients towards the end of the detailed design
period and discussed the procurement method. I explained that in the current climate there was a
shortage of builders that would tender for work. By bringing a contractor on board at this stage
accurate pricing can be carried out without the need to use a Quantity Surveyor. This pricing would
\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
10
determine the viability of the project and confirm if any changes would need to be made to the
scope or the budget of the project.
We explained the benefits of using a Quantity Surveyor in that they provide impartial advice on
costings and can be used as a benchmark against the received tender prices. The advantage of using
a contractor was that they would have up to date pricing and this is an advantage in a heated
construction market. The Client was more concerned with the work being of a high standard and
with a degree of price certainty rather than achieving the lowest initial price and opted to negotiate
with one contractor.
When selecting a contractor that might be suitable for this project we looked a number of builders
that would be suitable for the project and compatible with the Clients. We had a shortlist of two,
one I had recently worked with on a project and the other was the contractor that had worked on a
nearby house that the Clients admired. I had worked with both contractors before and both were
capable of the job but my preference was for ABC Construction (ABC). ABC was a larger company
with multiple crews and I felt they would be able to apply more resources to the project if required
and would be a better match with the Clients. I made my recommendation to my director and this
was discussed with the other Principal who had also worked with ABC recently and they concurred.
I then approached ABC to confirm their interest in the project. We arranged a meeting with the
Clients to see that each party was compatible, the Clients were impressed with ABC and took them
to a recent project he had completed (I was also administrating the contract on that project and this
was clearly stated to the Clients at the time).
3.1 Initial Estimate
In June 2008 ABC Construction were asked to submit an estimate for the project (house and garage)
to establish if the proposed design was within the Client’s budget. ABC Construction were supplied
with the following documentation
3
:
Cover letter
An outline specification
Existing and demolition plans
Floor plan and finishes proposed plans and finishes,
Proposed elevations
Typical longitudinal and transverse sections
Window and door schedule.
As this was an estimate, SCC-Tender forms were not used but the Contractor was asked to break the
summary into trades and this was based on how I set out Tender submission forms.
We received the estimate on 1 Aug 2008; I evaluated the breakdown of costs on a spreadsheet
4
.
This makes it easy to track changes and this is how I evaluate invited tenders. I identified a number
of items for clarification and I requested in writing that these be included
5
.
3.1.1 Revisions to estimate pricing
The estimate price for the house and garage was $510,134.33 incl GST. This was significantly higher
than the Client’s budget. On 19th August we met with the Clients and the contractor to discuss the
3
Estimate Package to XX; Appendix D-1
4
Tender Evaluation; Appendix D-1
5
Request for further information, Fax to ABC dated 03 Aug 08; Appendix D-1
\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
11
project. The Clients wanted to reduce the costs, but did not want to change the scope or reduce the
quality of the finishes.
It was decided to reduce the project cost that the Clients would carry out a number of items
themselves and post contract:
Interior Painting to be carried out by Clients
Floor coverings laid post contract
Garage painting by Clients.
Contingency sum reduced to $10,000.00 this was because the Contractors pricing was
thorough and picked up all possible options
Rimu skirting changed to paint quality pine
Clients would carry out the simpler demolition work themselves
This was communicated in writing to ABC Construction who then carried out re-pricing and the
revised estimate was $466,648.77 incl GST with the total for the house $431,434.81 incl GST. The
changes were tracked on spreadsheet
6
and after presenting this to the Clients
7
, they confirmed
they were happy to proceed to documentation based on this price.
3.2 XXXXXX Issue of Tender
On 19th February 2009 I requested that ABC Construction submit a fixed price to carry out the house
alterations. Since earlier pricing had been carried out, I requested that the same trade summary was
used
8
.
The tender package comprised:
Tender cover letter
9
– this includes a summary of provisional sums
Drawings for tender: Architectural, Engineering (and other consultants if required)
Specification: Architectural, Engineering (and other consultants if required)
Though not applicable in this case study, for tenders with multiple tenderers I include details for
visiting the site such as time and contacts.
3.2.1 Notice to tenderers
Notice to tenderers (NTT) cover items or issues that have changed or arisen during the tender
process.
This can be from a query from a tenderer and if this is verbal, I note that confirmation to the query
will be sent out in writing. I respond in writing and send this to all tenderers, I do this so all the
tenderers receive the same information. NTT can occur when an item or specification has evolved.
In projects this has occurred when a selected item was not going to be available in the time allowed
and an alternative had to be selected.
In this case study there no were NTTs as there had been earlier estimate pricing. Our practice has a
standard form for Notice to Tenderers. I email/fax the form and send a paper copy through the post
to all tenderers.
6
Tender Evaluation; Appendix D-1
7
Meeting minutes, 14th October 2008; Appendix D-1
8
Normally I would use NZIA SCC Tender Forms T1-T5 customized for the project
9
Request to submit a Contract price; Appendix D-1
\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
12
3.3 Tender Review
Once the tenders are received, I notify the Clients that the tenders have been received. We need to
evaluate these before presenting them to the Clients and I give indication of the period that I expect
to complete this in.
When evaluating the tenders, I do the following:
1. Check that all notice to tenderers have been received and followed
2. Tenderers have visited the site (if required on the tender form)
3. Tenderers have submitted their tender using the supplied forms
4. Create a spreadsheet with a breakdown of the trades as per Tender forms and input
each tenderers sums beside the trades. The spreadsheet includes margins and is useful
to compare tenderers.
5. Evaluate the tenderers tags and notes these on the spreadsheet
6. Note the subcontractors the tenderer has selected.
The spreadsheet is useful to compare the tenderers on each trade and I note if any figures seem
particularly low or high or contains errors. If figures seem low or if there appears to be an error I
notify the tenderer in writing asking them to confirm the tender cost figures.
When tender clarifications are required, I notify the tenderer in writing listing the items of
clarification required and supply a date that these clarifications have to be confirmed in writing by.
This is usually a period of one week and if a number of tender clarifications are required, I ensure
they are all sent out at the same time to ensure fairness to all the tenderers.
When not all the tenderers have clarifications I contact them via email or fax and confirm that we
have received their tender and these are being evaluated. I will give an indication of when we
expect to reach a decision from the Client.
When there is delay in the tender acceptance, I contact each tenderer in writing and state the
reason for the delay. This is usually if the work requires government approval or approval from
different departments within the same organisation.
3.3.1 Tender Review for XYZ Project
ABC Construction submitted a fixed tender price of $407,635.50+gst on 25th March 2009
10
. I carried
out the above steps (9.3 Render Review) and evaluated the tender in relation to the earlier
estimates received. There were increases to the labour cost, I thought the increases were
reasonable and after discussing this with our director they were deemed acceptable. We felt there
was still a need to reduce the project cost and I discussed with ABC Construction ways to reduce
costs. Two options were proposed:
Use an alternative kitchen manufacturer The kitchen design had not been finalized but it
was clear that the initial sum of $35,000.00 was likely to be too low. Using an alternative
supplier would offer savings of around 20% but the quality would likely be lower.
Use a charge up system for labour and materials this transfers some of the risk from the
Contractor to the Principal. This means that only time and materials used will be charged.
10
Tender price for house alterations; Appendix D-2
\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
13
I discussed these options with the Clients but they preferred to use the original joiner and a have the
certainty of a fixed price
11
.
During the Tender stage, the Clients advised that they will be sourcing the light fittings through an
Interior Consultant and that one of the skylights had been deleted. I communicated these changes
to ABC Construction and advised a revised contract price of $401,985.00+gst. This was accepted by
ABC Construction.
With the provisional sum for the lights removed, the Clients accepted ABC Construction fixed price
on 14th April 2009
12
.
3.4 Tender Acceptance
In the case of an invited Tender, I call the successful tenderer confirm verbally that their tender was
successful; our practice has a standard tender acceptance letter accepting the tender on behalf of
the Principal. I also instruct the Principal to confirm the tender acceptance in writing and this, along
with our practice letter constitutes part of the contract documentations
13
.
On 17th April I sent out the letter of acceptance to ABC Construction and began to compile the
contract documents. This letter confirms the status of the project and instructs the contractor to
notify sub contractors.
For invited tenders, our practice has a standard notification to unsuccessful tenderers. This follows
NZIA guidance
14
and states who won the tender and lists the tenders received. If applicable it also
requests the return of the tender drawings and specification.
4 XYZ Project Contract
I discussed the type of contract to use with the Principals. The project at the limit of the short form
agreement. The primary differences between SCC-1 and SCC2007 SF were that –SF did not have
provisions for:
Payment for offsite materials
Cost fluctuations
The use of Bonds (Contractor, Principal, in lieu of retentions)
Liquidated damages
15
None of these were being used in this case study and it was agreed that –SF contract would be a
suitable contract for the project.
4.1 Principal
In December 2008, I had begun compiling the contract for the garage and confirmed with the Clients
the legal name of the Principal and names of separate contractors
16
.
11
Email to Clients on ways to reduce costs; Appendix D-2.
12
Email to Clients on ways to reduce costs; Appendix D-2.
13
Tender Acceptance Letter; Appendix D-2.
14
NZIA Practice Note PN9.301
15
Liquidated damages are an amount based on losses the Principal would be expected to incur if the contract
works are not completed in the agreed time. XXX does not generally use liquidated damages. In this case
study there were no limitation on the completion date. The Clients had alternative accommodation and were
not constrained by use of this accommodation. Without liquidated damages, general damages could still be
claimed under the Consumers Guarantees Act 1993 but these have to be proven and incur costs in making a
claim.
\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
1
4
In this case study, the Principal for the contract were the Clients. The name of the Principal may not
be the name of the Clients and I have encountered this when work is being paid for, and on work a
property owned by a trust. The contract will need to be signed by the legal guardians for the trust.
A Principal representative may be appointed and they will handle matters relating to the
administration of the contract.
If the Principals address for submission of payment claims is different from the Principal address this
needs to be listed. When our practice are administrating a contract payment claims then the claims
address is the office address.
4.2 Contract documents
In addition to contract schedules and drawings this included
17
:
Principal’s tender acceptance
Our practice letter of acceptance
Post tender correspondence
Contractor tender submission
4.3 Warranties and Guarantees
The warranties and duration required were listed in Rule 4.4 and in the Masterspec Specification.
This form was to be used for all warranties or as per Standard conditions of contract Rule 3.6
alternative forms that comply with the wording of SCC-SF2007 4
th
Ed Schedule E1.
4.4 Insurance of Contract works.
The project was additions and alterations to an existing property and Insurance of the Contract
works was by the Principal and included for Consequential Loss. Following discussions with the
Contractor it was established that these were to assume a start date of 1
st
April 2009
18
.
4.5 Public Liability Insurance
This insurance is provided by the Contractor and as per NZIA SCC-SF2007 4
th
Ed Rule 5.3.1 covers
liability that arises from performing the contract works. The contractor has Public Liability insurance
of $5million and a certificate of currency was provided and included in the contract.
4.6 Contractors Vehicle Insurance
This covers risk to a third party though use of the vehicle, not the vehicle itself. A certificate of
currency was provided and included in the contract. The Contractor had a general Contractors
Vehicle Insurance policy, this expired during the construction period and I requested a new
Certificate be sent through before the certificate expired.
4.7 Site Possession date
The site possession date was set as 5 working days after the Tender Acceptance. This is the default
period and allowed the required insurances to be put in place
19
. The contractor was already onsite
as construction of the garage was underway.
4.8 Final payment claim
The contract used the default period of 2 months from practical completion.
16
Email from Clients dated 9 Dec 2008; Appendix D-2
17
Contract Documents; Appendix D-2
18
Meeting minutes dated 25 February 2009; Appendix E-1
19
This is as per PN9.401 which suggests 5-10 working days after award of contract.
\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
15
4.9 Principal supplied items
Principal supplied items are items that are supplied by the Principal and installed by the Contractor.
This is usually because the Principal already has those items or can purchase them. The Principal
needs to insure the supplied items and carries full responsibility for these even after they are
installed.
The disadvantage of Principal supply items is that items need to be correct, in sufficient quantity and
fit for the intended role. I always advise the Clients that while they may save some costs by
spending time selecting and supplying the items themselves. There can be occasions where parts
may be defective or missing and it is then the Principal’s responsibility to replace the items. If the
contractor/sub contractor or the Architect has to arrange for replacement parts then there will be
additional costs that may outweigh any savings they have made.
Principal supplied items for this contract were
Heat pumps
Kitchen Appliances
Light Fittings
Bathroom extraction fans (excluding ducts).
Refer to Section 15.6 for how these were handled in this case study.
4.10 Separate Contractors
For this Contract, there was a separate contractor for data, audio and phone services. The
Contractor was made aware of this during the procurement process.
The Contractor is to work alongside the separate contractors but is not responsible for the
performance of the separate contractor. A Contractor and Principal need to be clearly advised of
the co-ordination and responsibility of the separate contractor. The Contractor should be
responsible for the site safety and the contract insurance (in this case by the Principal) should
include the separate contractor. This will eliminate potential disputes of what is required of them to
work with as there will be time/cost coordinating with separate contractors. The liability of the
separate contractors needs to be considered, where possible it is better to use nominated sub
contractors in place of separate contractors.
4.11 Monetary allowances.
4.11.1 Prime cost sum:
A prime cost sum is a sum allowed for the supply only of items to be installed by the contractor. The
Contractor is to allow to install these items elsewhere in the contract. The sum does not include
Contractor's installation costs, margins, overheads or profit
20
. These sums are typically for fittings
that have not been selected or finalised during the documentation stage. The profit should be
stated as a percentage and included elsewhere in the contract price.
In this case study there were a number of prime cost sums
21
:
Door/window hardware
Bathroom/Ensuite Joinery
20
Practice Note PN9.302 and http://www.thegrad.net.nz/Forum-Have-Your-Say/Prime%20Cost%20sums%20-
%20definition-i6e193641-7e4f-41ba-8177-86ea62ce3b06-1114.htm
21
Prime Cost sums in Contract; Appendix D-2
\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
16
Plumbing Fittings and fixtures
Kitchen Joinery
Verandah Brackets
Glazing – mirrors
Storage cupboard doors
4.11.2 Provisional sums
A provisional sum is a sum that has been allowed for the supply and installation of a particular
product or service. The sum will include for the Contractors margin and Preliminaries & General
(P&G).
This case study had a provisional sum for the exterior painting of the new addition only.
4.11.3 Contingency Sum
A contingency sum is an amount set aside to be used at the direction of the Architect for unforeseen
items. For alteration work, this is important as some elements are not visible until after construction
work has begun.
In this case study, we had initial contingency sum of 5% of contract value. This was reduced during
the estimate pricing to $10,000.00 as the pricing breakdown was very detailed and we thought that
would suffice. NZIA suggests a range of 5-10% depending on the work
22
.
4.12 Practical Completion
The Contract provided a timeframe of 180 working days to achieve Practical Completion. The
Contractor was required to use SCC-SF 2007 4
th
Ed Form C1 Contractor’s Advice of Achieving
Practical Completion.
4.13 Defect Liability Period
A defects liability period is a set period where the Contractor is liable to remedy any defects that
occur during this time. This contract had a Defect Liability Period of 3 Months. This the default
period in SCC-SF2007 4
th
Ed.
4.14 Retentions
Retentions are a monetary sum to be retained to ensure the Contractors carries out the Contract
Works in full and corrects any defects that have arisen during the defect liability period. The amount
held for retentions was 10% for first $200,000.00 and 5% for the remainder of the contract price.
The contract were as per SCC-SF2007 4
th
Ed with 40% released at practical completion and 60% at
the end of the 3 month Defect Liability Period.
4.15 Final Payment Claim:
This is maximum time after Practical Completion that the Contractor must submit a final claim. For
this contract it was set at 2 Months, this the default period in SCC-SF2007 4
th
Ed.
4.16 Special Conditions of Contract
There were no special Conditions of contract in this case study.
22
Practice Note PN9.510
\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
17
Special conditions of contract modify the standard conditions of contract and these need to be
clearly listed and explained to the Principal and the Contractor. They are commonly used to change
the balance of risk between the Principal and Contractor.
In other projects, I have used Special Conditions of Contract in the following instances:
In a residential project, an amount for retentions is being deducted at the practical
completion stage and will be held for the duration of the defect liability period.
I have worked on a civic refurbishment project, where the hours of work were to be around
meetings. When assembling the tender documents, this was listed as a special condition
and I included the dates and times where work could not occur and tenderers were to
include afterhours hourly rate.
4.17 Signing of contracts
The contracts (Standard Conditions and Specific Conditions) were sent out for signing on 23
rd
April
and the Principals signed and initialed each page and the sections highlighted. After being signed by
the Contractor, our practice retained the Principal’s copy for the duration of the contract.
5 Other types of contract
5.1 NZIA SCC-2009
NZIA SCC-2009 is the standard NZIA contract for when the contract administration is being carried
out by a member of the NZIA. The Contract is suitable for all range of projects and complexities.
The Contract provides a Practical Completion Certificate and Defects Liability Certificate. I have used
the SCC Contracts for new houses and commercial work. The Contract is much more comprehensive
than the Short Form Contract and includes provisions for the following:
Bonds
SCC 2009 provides for provision of the following bonds:
Contractors Performance bond
Contractors Bond in lieu of retentions
Principals Bond
A Contractors performance bond is a document between the Contractor and the Principal that
provides financial protection against the Contractor defaulting. The Bond is executed but the
Contractor and the Surety named in the Bond. The Surety named in the Bond is the party that
provides the financial protection. The use of Bonds in generally more suitable for commercial work
and projects over $ 1.5 million
23
. The requirement for a bond for included for is to be noted in the
Tender. A Principal’s bond and Contractors Bond in lieu of Retentions are not common practice.
Our practice does not use bonds.
Fluctuations in Cost
This provides for when the cost to supply material will fluctuate over the Contract period. This is
likely to be on Contracts greater than 12 months .
Payment & Security for Offsite Materials
This is for items and materials that are being stored of site for the benefit of the Principal. When this
is used, our practice requires the items and materials are clearly labeled property of the Principal
and ask for photographic evidence of this.
Liquidated damages:
23
NZIA Practice Note PN9.404
\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
18
Liquidated damages are an amount based on losses the Principal would be expected to incur if the
contract works are not completed in the agreed time. Without liquidated damages, general
damages could still be claimed under the Consumers Guarantees Act 1993 but these have to be
proven and incur costs in making a claim. Our practice does not generally use liquidated damages.
Contractors Construction Machinery Insurance
Includes equipment and machinery owned by the contractor and required for the contract works.
While not a requirement of the Contract, these were provided by the Contractor for this project.
Nominated sub-contractors
A subcontractor may be nominated because they provide a specialised service and/or have worked
with the Principal for a period of time. Nominated subcontractors and their scope of work need to
be listed in the tender documents. The Contractor has the same responsibilities for a nominated sub
contractor as they do for selected sub contractors.
I have worked on residential project where a plumber was to be nominated sub contractor as they
had carried out previous work on the property. In these situations, unless the service is specialised I
recommend to the Principal that the tenderers can get this priced by other providers as well.
In the commercial projects I have worked on nominated sub contractors are typically been for
security services and Information Technology services and where suppliers already carry out all
associated work and maintenance for the Principal.
5.2 NZIA SCC-SF 2009
The short form agreements are for use on house alterations or new buildings that are simple in
nature and for projects of a low value with a short contract period (under a year).
The layout is similar to SCC-2009 but the following provisions are not allowed for:
Fluctuations in cost
Schedule of Quantities
Contractor’s Performance Bond
Contractor’s Bond in Lieu of Retentions
Producer Statement – Construction
Confirmation of insurance construction plant and equipment
Earlier versions of SCC-SF did not allow for payment for offsite materials.
5.3 NZIA National Building Contract- General
The latest version is July 2010 and the layout is based on the NZIA SCC-2009 contract. The previous
version, NZIA NBC-G 2003 was based on the NZIA SCC1-2000.
I have used NBC-SW 2003 for house alterations that are not being administered by XXX.
5.4 NZIA National Building Contract short form
The short form agreement is used for smaller projects and is based on the layout of NZIA SCC-
SF2009. Like the NBC-G, it is used for projects that are not being administrated by an Architect.
5.5 NZS3910
NZS3910 is similar in scope to NZIA SCC contracts. It is commonly used by Engineers and can be used
by Contractors that have design responsibility. One difference between NZIA SCC contracts and
NZS3910 is that in NZS 3910 50% of Retentions are released at Practical Completion as opposed to
SCC’s 40%.
\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
19
6 Reflection
The estimate pricing by the Contractor was the right procurement method for this project, as the
Clients wanted a high quality of work and a degree of price certainty. By bringing the Contractor
onboard early meant we were able to identify where savings could be made. Having worked with
the Contractor before I knew that the estimate would be broken into sufficient detail but in hindsight
the SCC tender forms should have been used and I now use these for all estimate pricing. The tender
for the house alterations was not as formal as it should have been. In part, this was because the
Garage was under construction and earlier estimates had been carried out. However, all tender
should be treated consistently.
In hindsight, SCC2007 would have been more suitable for the project as the monetary value was
reasonable high for an alteration project and now I would recommend using SCC 2009 for similar
projects. The contracts were not signed till 3 weeks after construction began. These should be
signed before Contractor begins onsite but this is not always practical.
\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
20
Example 4
D. PROCUREMENT
ABC Project
Applicant Involvement 95%
1. Project Rundown
Project Type
Retail
Project Building Area xxxxxm2
Anticipated Construction Cost $xxxx (Based on Tender)
Commissioned Inception: December 2009
Completion: August 2010
Client xxxx
Architect xxxx
Structural Engineer xxxx
Quantity Surveyor xxxx
Refrigeration Engineer xxxx
Electrical Engineer xxxx
Hydraulics Engineer xxxx
2. Project Précis
The project was the refurbishment of an existing building in Eketahuna. It consisted
predominantly of an internal fit out including alterations to the xxx, xxx and xxxx, the addition
of new xxxxx, xxxxx and xxxxx throughout. The external envelope included new signage
incorporating the new branding and painting to all elevations.
The client is one of our practices main clients. We carry out a lot of refurbishment work as
well as new builds. I am currently assisting a Project Architect with Contract Administration
on a new building in Matakana. As well as this I am running a number of other refurbishment
projects around the greater Dunedin area.
\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
21
3. Applicants Role
My role was similar to that of “Project Architect”. I was involved from the Detailed Design
stage right through to the contract administration and Defects Liability Period. I was
responsible for producing working drawings for building consent and coordinating consultant
and tender documentation through to construction stage. As it stands the project is currently
nearing the end of the Defects Liability Period.
D.1 Preferred Construction Contract
The preferred form of contract by our Client for this type of work is NZS3910. I am more
familiar with this form of contract as all our Client’s work in the office falls under it. The Client
doesn’t need a Registered Architect to administer NZS3910 as it is done so by a third party,
namely an ‘Engineer’. SCC 2009 is typically regarded as more Architect focused in this
regard as a Registered Architect is required to administer it.
NZS3910 was initially tailored towards Civil Engineering, however there is a greater depth of
industry involvement when using this form of contract for large construction projects. The
SCC format is simpler and in order of building process. Both forms of contract are
recognized as two of the most commonly used forms of contract in New Zealand and both
were developed through industry consultation.
D.2 Specific Conditions of Contract
The Specific Conditions of Contract include information relevant to the specific project.
D.2.1 Performance Bond
A Contractors Performance Bond - 10% of the contract price was included to protect the
Principal against non performance of the contractor. The two types of performance bonds
are:
- On Demand Bonds
Surety required to make payment whenever the bond is demanded
- Conditional Bonds
Bond conditional upon proving the amount of loss suffered
\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
22
Under NZS3910 the bond can be called upon whenever the contractor is in default.
D.2.2 Insurances
Insurances fall under Specific Conditions of Contract in NZS3910. The Architect does not set
the amount of Insurance. The Client sets it or it is deferred to an insurance advisor. This was
an alteration to an existing building; therefore it was the responsibility of the Principal to
effect insurance in the joint names of the Principal and the Contractor. Our Client’s have a
policy of taking out Contract Works Insurance for New Build’s also.
Insurances should be in place before any works take place on site. This was discussed at
the Pre-Start Meeting by my Project Architect with me present.
D.2.3 Liquidated Damages
Liquidated damages reflect the level of foreseeable loss that the client has calculated to the
best of their ability on similar projects. LD’s set in the conditions of contract were initially $xx
per calendar day. They were raised on this project to $xx. This is a reflection of the need for
increased liability on behalf of the Contractor as finishing at Practical Completion is of great
importance in our client’s work. See Appendix 4.1 for NZS3910 Conditions of Contract.
D.3 Special Conditions of Contract
The Principal has their own set of special conditions that the Tenderers must uphold to with
this type of work. Due to the volume of the work that they build being all very much the
same, they are able to have generic special conditions. Within these they tailor things to their
own needs.
Where extensive Special Conditions are applied to a contract, the Client is seeking to
change the risk allocation, resulting in a higher bid price from contractors trying to cover the
added risk being applied to the construction phase of the project.
Tenderers may add tags to try and manipulate the meaning of the Special Conditions to suit
their own version of the contract. In most cases these are not accepted by myself or my
Project Director as we know the Principal will not accommodate changes to them.
D.4 Other Types of Construction Contracts
NZIA Standard Conditions of Contract (SCC2009)
\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
23
-
Contract between Principal and Contractor for any size and complexity where the architect
administers the contract on behalf of the Principal. The Architect must be a Registered
Architect.
NZIA Standard Conditions of Contract Short Form (SCC-SF 2009)
- Similar format to above but intended for alterations or new build of simple nature.
Reasonably short contract period.
NZIA Standard Conditions of Contract (MW2)
– For Minor Works
NZIA National Building Contract (NBC-G 2003)
-
Contract between Principal and Contractor for any size and complexity where the Architect
is not engaged to administer the contract.
D.5 Forms of Contract
This was a Lump Sum Contract (agreement by which the Principal agrees to pay a
Contractor a specified amount for completing a scope of work without requiring a cost
breakdown). This is a traditional type of contract commonly used where by the contract sum
is largely determined before construction begins.
D.5.1 Other forms of Contract
Cost Reimbursement Contract
- Contract figure derived from actual cost of labour and materials with sums for overheads,
profit and co-ordination added.
Partnering Contracts
- Multiparty Contract whereby Consultants and Specialist Sub Consultants are party to the
contract. There is a great deal of flexibility with regard to procurement route.
Guaranteed Maximum Price (GMP)
- Contract that establishes a price for a specific scope of work that cannot be exceeded.
They are used on Fast Track projects or when the design is incomplete at the time
construction starts. Quality can suffer.
Turn Key
- Project in which is constructed by a Developer and sold or turned over to the buyer in ready
to use condition. The Developer handles all decisions and problems related to construction.
Labour Only
\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
24
- Contract whereby the Client manages the whole process and the contractor is only
responsible for building. The Client has better control of the building process and manages
sub trades.
D.6 Contract Procurement
Our Client can be described as a Client who is experienced and are able to select
a procurement process that works for them, taking into account their prioritized
objectives and their attitude to risk.
D.6.1 Preferred Type of Procurement
A Selected Tender was the preferred option for this type of work. Our Client has a list of
Contractors that they have had a good working relationship with in the past. Added to this
are Contractors that through word of mouth the Client has heard positive feedback about.
On projects with a budget of 500K or less, generally up to 4 tenderers are selected. Reasons
for this include cost savings that need to be achieved to meet a tight budget. On projects of
greater than 500K in value, up to 5 tenderers may be selected as there is greater potential
for one tenderer to pull out. By increasing the pool of potential Builders an increase in
competition can be gained between them and a more cost competitive tender achieved.
This project resulted in the Client choosing five. The state of the economic climate at the
time with the country coming out of recession late last year meant Construction Companies
were desperate for work and this increased the potential for a very good tender price for the
Client. With this process it is also important to be aware that Contractors desperate for work
may tighten up their price too much and therefore compromise quality.
D.7 Other Types of Tender
D.7.1 Negotiated Tender
Advantages: Will not cut corners in pricing, ensure quality is not compromised. Ensure
tender is market related – Quantity Surveyor engaged to review the tender quantities and
costs
D.7.2 Open / Public Tender
Advertisement, registration of interest and pre-qualification assessment
\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
25
D.7.3 Preliminary & General (P&G) and Margins Tender
Advantages: Ability to Fast Track - Time constraints and very thin documentation. Main
Contractor on board early and documents produced alongside them.
D.8 Other Types of Procurement
Design & Build
- A procurement type whereby design and construction can be assigned to a single party.
Singular responsibility in terms on contract quality cost and schedule.
Fast Track
- A procurement type whereby stages may overlap to reduce the overall programme. Project
can be divided into different packages. Requires a clear scope.
D.9 Tender Process
A standard tender process is followed at our practice:
D.9.1 Tender Register
I sent out this standard office document listing all tenderers, their points of contact and
addresses. This was reviewed by my Project Director. Once the client had confirmed their
list of Tenderers I rang all to engage them verbally and confirm all of their details. The
register includes a column beside each tenderer that records who, when and how the
documents were picked up and delivered in order to allocate time fairly. See Appendix 4.2
for Tender Register.
D.9.2 Invitation to Tender
I sent out this standard office document formally engaging the tenderers which was reviewed
by my Project Director. It acts as a record of all the Tender documents being sent out
including all Consultants documentation. At the bottom it lists the tenders period and closing
date. A drawing register is attached to this also. During the tender process one of the
tenderers pulled out due to landing another contract. The Project Manager (PM) was not
impressed as that particular tenderer had been particularly keen to tender for the work. This
highlights the need to increase the pool of potential Contractors as a tenderer can pull out at
anytime without warning. The tender documents were returned to our office. See Appendix
4.3 for Invitation to Tender.
\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
26
D.9.3 Notice to Tenderers
I sent out these standard office documents which are used throughout the course of the
tendering process. They answer tender queries and clarify items that may have been missed
or have been added to since the tender drawings went out. Whenever a query is answered it
is sent to all respective tenders to keep it fair across the board. They need to be clear and
unambiguous using words like ‘add’ and ‘delete’. These documents are kept confidential
between all parties. See Appendix 4.4 for Notice to Tenderers.
D.9.4 Tender Analysis
Four tenders were received (three by fax and one by email). The two that came in by fax
were late by 8 minutes and 12 minutes respectively. The PM concluded that they were still
legitimate as the extra time would not have given either any significant advantage, however
it was our recommendation to return the late tenders. (See D.10 Commentary for
breakdown).
Of the four tenders, one was particularly high, two were similar in the mid range and one was
particularly low. The QS wanted to shelve the lowest tender from the outset as he believed
from past experience the Client would not want to deal with such a low offer as there would
be pitfalls when it came to them carrying out the job efficiently. They were a large
Construction Company that had worked with the Client on comparative jobs many times
before. The PM proceeded to give them a phone call and establish whether they could
actually do the work for the price submitted.
D.9.5 Tender Correspondence
I sent three out of the four tenderers correspondence letters that replied directly to their
tenders, verifying tags and requesting extra information where necessary. The favored
tender at this stage had a list of erroneous tags that I requested be removed as they were
not compliant to the conditions of contract. See Appendix 4.5 for Tender Correspondence
Letter.
D.9.6 QS Tender Report
The QS then submitted a Tender Report based on the tenders received to establish a
method for ‘comparing apples with apples’. It provided a cost breakdown and
recommendation to the Client as to the most appropriate tender. See Appendix 4.6 for
Tender Report.
\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
27
D.9.7 Tender Acceptance
The Client confirmed through the PM who they preferred. I sent out a Tender Acceptance
letter to the winning tender and likewise tender decline letters to the unsuccessful bids. Often
the winning tender price is released; however disclosure of that information must first be
determined by the Client. In this case, our client chose not to allow that information to be
included on the Tender Decline Letter . The low fee nature of these projects demands
efficiency. These documents are based on standard NZIA
Pro-forma letters. See Appendix
4.7 for Tender Acceptance Letter and Appendix 4.8 for Tender Decline Letter
D.10 Commentary
The Registered Architects Rules 2006 state under the Code of Minimum Standards of
Ethical Conduct that A Registered Architect must:
- ‘Uphold the Law
- ‘Exercise unprejudiced and unbiased judgment’
- ‘Act with honesty and Fairness’
A late tender, no matter how late, is still a late tender. Best practice is to return it unopened
to the party concerned as it is the only way to be fair and impartial across the board. In this
case we recommended to the PM what a prudent Architect would adhere to and left it to him
to decide the outcome.
A Breach of Tender is a breach of contract and therefore a breach of the law. An invitation to
tender (invitation to treat) is not a contract per say but the distinction between the two is not
always clear. The law generally considers invitations to treat as “Contracts that govern the
procurement process” to avoid injustice. The law therefore requires all parties operating
tenders to act fairly and in accordance with the advertised procedures or risk being sued for
damages such as tender costs and loss of future profits.
My Project Director and I are assessing how to handle this situation the next time it arises.
First and foremost it is about acting as a prudent Architect fairly and impartially. Secondly it
is about transferring liability onto the party obliged to have the final say if you as the Architect
see any breach in standard of ethical conduct what so ever. See Appendix 4.8 for Email
from Construction Contracts Lawyer.
\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
28
Example 5
D. Procurement
During developed design, senior architects A and B discussed project delivery strategies with our
client. They believed the most appropriate strategy would be a traditional linear approach: design,
documentation, tendering, construction and occupation. The advantage of a linear programme is that
the client can maintain greater control over the budget and design at each project stage. Pricing also
occurs with a full document set in place, so can be more competitive. The downside is that it is a time
consuming process due to its sequential nature. It is also near impossible to complete an error-free
documentation set, so the client cannot assume that the tender price will be the ultimate project cost.
Other Procurement Options
Fast Track
Design/documentation and construction phases are overlapped – documents are usually prepared in
a series of trade packages. The client often establishes a contract early with a contractor (the tender
may be on only P&G and margins, with a budget set for balance of works). The contractor is then
often involved in managing the design delivery to meet the procurement requirements. Project
consultants may or may not be novated.
Advantages:
Good for larger commercial projects with critical time deadlines, as overlapping saves time.
Client may achieve earlier cash flow, building sale or occupation.
Disadvantages:
Involves more project administration and prolonged dealings with Territorial Authorities (e.g.
staged and multiple Consents, amended Consents due to modifications).
Greater scope for errors as work is built with incomplete documentation.
Less competitive price wise – extra administration costs, trades being brought to site
repeatedly instead of carrying out all associated work in one time period.
Won’t produce innovative design results.
Design and Build –
The project is organised around a single contract (which includes all consultants needed), which can
avoid adversarial relationships associated with traditional tendering method.
Advantages:
Can be either a linear or fast track process.
Encourages collaboration between the architect and contractor, with the contractor providing
input during all design stages.
Client has a single point of contact and a single party to hold accountable.
Costs are considered earlier in the design process, before detailed drawings are completed.
Encourages application of cost-effective building technologies.
Disadvantages:
Possible loss of design control by architect in the interests of trying to achieve cost savings.
There is no opportunity for competitive tendering.
Client does not have a clear idea of how the project price is made up.
Novation –
The architect produces documents for the client up to a certain predetermined stage (usually the end
of developed design, when the design is set and costings have been carried out). A contract price is
sought and a contractor is selected on the basis of these documents. The architect’s contract is then
\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
29
transferred from one party to another (i.e. from the original client to the contractor) and the contractor
takes responsibility for design management and project delivery to completion. The party you were
originally contracted to has an obligation to discuss novation terms with you, and the original party
cannot novate you without your consent. You must also ensure there are no terms in the novation
deed that extend your liability or scope of works beyond the scope of the original agreement.
There may be several contract documents required:
Consultants’ agreement, covering normal conditions of engagement and scope of works for
architect (stage 1 between principal and architect, stage 2 between contractor and architect).
Deed of Novation (brings together the principal, contractor and architect). It sets out novation
conditions and covers items like responsibility for fee payment and liability issues between
principal and contractor.
Building contract (between principal and contractor). The architect is not directly a party to it,
but is affected by it to the extent that it covers consultants’ roles and responsibilities after
novation.
Deed of Covenant (requires consultant to act impartially between all parties named on deed).
Advantages:
Can reduce risk of cost and time overruns by allowing design consultants and contractor to
work together efficiently. The contractor takes on the onus of design management and
construction methods can be tailored to the contractor’s preferred systems.
Allows client to focus responsibility during documentation and construction on a single party.
Time savings – a price is often agreed before the drawings are completed. Design processes
can also overlap construction processes (fast track) to save time.
Client has a greater control of the design (via scheduled design reviews etc) than under a
Design and Build process.
Disadvantages:
Gives contractor significant control over the design (this can happen at an early stage and
the client may not understand the implications of this on the final design).
Not all contractors have the dedicated resources or suitably experienced staff (including a
suitably experienced project QS) to undertake effective design management.
There is no established format or documentation for novation. The overall contract documents
may be assembled by specialist construction lawyers may seek to transfer risk to (and
increase liability of) consultants. Documentation must be reviewed by the architect’s PI
insurer and lawyer before signing.
A novated architect cannot be the client’s independent representative (due to a conflict of
interests) and cannot certify payments to the contractor.
Guaranteed Maximum Price
The contractor prices a job based on an incomplete drawing set and an outline specification (often at
the end of developed design, when the contractor still has the ability to vary the work to maintain the
price and programme) and fixes a maximum project price. However, only the client (not the
contractor) has the ability to vary the scope of the project. The contractor puts forward his price for
preliminaries and general, and his margin, while tendering each sub trade as further documentation is
provided. This arrangement is often used on fast track projects. The architect still has a duty of care
to the client, to ensure that the client ends up with the quality of building they expect.
Advantages:
Time savings – the project does not have to be fully documented before a price is obtained.
There is no cost penalty to the client for time delays.
Gives the client price certainty.
If a cost/risk sharing arrangement is in place between client and contractor, both parties share
financial rewards if a project component’s cost is lower than its estimated ‘maximum’ price.
Disadvantages:
Quality can be at risk unless project documentation is very thorough. If quality is not clearly
established at the outset, it may be compromised to meet the budget.
The client pays a premium for having a price assured (as contractor carries the cost risk).
\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
30
If cost savings are required, this may involve redrawing (which can put time pressure on
consultants and result in inefficient use of time or in drawing mistakes being made in haste).
Possible greater liability for consultants (especially if they have been novated to the
contractor) as the contractor may reduce contingency sums to a minimum to secure the job.
NZIA SCC – Standard Conditions of Contract
NZIA SCC 2007 (1
st
Edition) was the chosen form of contract due to the project’s size. The client had
been provided with a copy of SCC to review early on in the project and had met with senior architects
A and B to go through the document and discuss the clauses. The client therefore knew that the
project would be run as a lump sum plus variations contract, following a selected tender process.
SCC is an agreement between the contractor and principal, but clearly defines the architect’s role
to administer the contract impartially on the principal’s behalf. SCC and SCC Short Form are the only
documents generally recognised within the industry which provide for an architect’s role during
construction.
Other Commonly Used Contracts
NZS3910 – operates in a similar manner to SCC, allowing for an ‘engineer’ to impartially administer
the contract and act as the principal’s agent and advisor. It includes several similar features as SCC
such as a provision for retentions and bonds.
NZS 3915 – an agreement between the principal and contractor. It is based on NZS3910, but altered
to accommodate having the principal managing the contract. The contract drawings and specification
can be prepared by either principal or contractor. If a dispute arises the principal and contractor can
call on an agreed expert to make a decision.
NZIA National Building Contract Generalan agreement between the principal and contractor. It
follows a similar format to SCC, but all references to ‘architect’ are removed and replaced with
‘principal’ as there is no architect engaged to administer the contract. However there is provision for
the architect to act as the principal’s agent in some circumstances. NZIA NBC SW (Small Works) is
similar to SCC-SF, so is suited for simple projects with a relatively low value.
Contract Works Insurance
The insurance provisions of SCC require that either the client or the contractor are to effect and
maintain insurance cover for the full value of the new work. Because the project was a new build, the
contractor would be responsible for arranging contract works insurance. To make the client aware of
what level of cover would be appropriate, we sent a practice project insurance memorandum
(appendix 20) which listed some suggested figures ( our director reviewed the figures before I sent
the document off). The client was required to discuss the values with their insurance provider and
seek their advice and confirmation. Once we had written confirmation from the client that this had
occurred, we included these cover values in the copy of SCC 2007 (Schedule B1 – Specific
Conditions of Contract) included as part of the tender documentation.
If the client were responsible for the contract works insurance, a similar memorandum would have
been sent to them. Again we would suggest insurance values based on our experience, for the
client's insurance provider to confirm. Architects are not insurance experts so the client (and their
insurance broker) needs to take responsibility for ensuring suggested insurance values are adequate.
The client must confirm the excess on their insurances, as the contractor would be required to pay the
excess for a claim (for any loss or damage to either the contract works or existing structures). Ideally,
the client would organise contract works insurance with the same insurance provider that covers the
existing building to make sure the two insurances are compatible, and increase the amount insured.
Existing structures should be insured to full replacement value (less the value of any portions being
demolished).
Monetary Allowances
Amounts were nominated in our tender documents for certain monetary allowances. Allowances in a
contract are useful when a part of the contract works has yet to be sufficiently defined or detailed to
enable it to be priced.
\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
31
Prime cost sum
This is a materials related monetary allowance. This sum includes the net purchase price and supply
to site of a specific material to be part of the contract works. It also includes a reasonable allowance
for the contractor's cost and profit, but does not include costs associated with the material's
installation. A prime cost sum is used for materials where all other parts of the work involved in
incorporating the materials into the contract works can be costed. Where installation work cannot be
costed, these items should be included as provisional sums. The architect should clearly describe
prime cost sums as without thorough descriptions, tenderers might not allow correctly for the items
installation.
Provisional sum -
This means a work or item related monetary allowance. The sum covers the cost of carrying out a
specific part of the contract works, or for items that the contractor pays for. It includes for both
materials and installation, as well as covering all of the contractor's cost and profit.
Monetary allowances are not variations to the contract, so should not result in an extension of time.
When there is a difference between the relevant allowance and the actual amount spent, the contract
price must be adjusted to take account of the difference. Items covered by a monetary allowance can
be deducted – having a sum is not a guarantee that the work will be carried out. However, the
principal has no right to carry out the works or arrange for others to do so.
Contingency sum
The practice always advises clients to allow for a contingency sum within their project budget. This
sum is to cover costs of work unknown at the time of entering into a contract, and needs to include
includes all the contractor’s costs and margins associated with carrying out the unknown work. A
contingency sum should reflect the complexity of the project and any unknown factors, such as
foundation conditions. The spending of contingency sum (in terms of both time and amounts) is
directed by the architect, but is authorised by the client. Therefore the client must be kept informed of
spending as it occurs. As the contingency is spent, the contract price must be adjusted by the
difference between the total spending authorised by the architect and the sum stated in contract
documents.
The contingency sum for the contract was $50,000.00 excluding GST, which totalled approximately
7.5% of the project cost as provided in the latest QS estimate. However, the contingency sum was
not declared in the contract. This issue was discussed with the client – as with other past projects,
the client was advised to keep the contingency sum separate from the contract as including it may
give some contractors the impression that the money is there to be spent.
Liquidated Damages
Liquidated damages are a genuine pre-assessment of the loss that a client will suffer if the
contract
works are not completed on time, not a penalty for late completion. Damages can also be calculated
on the basis of lost interest that would have been earned (or the cost
of extra interest on borrowings)
due to a delay in completion of the contract.
The amount set for liquidated damages if any, must be written into the contract. An architect must
advise their client that liquidated damages are available as a remedy but must not set the amount of
damages. If liquidated damages are set and included, the architect must show them as a deduction
from certified
progress payments issued after the due date for practical completion (after allowing for
any extensions of time).
For this project, the client would have suffered no financial loss had the contract works been
completed late as they owned the land and had yet to hire staff for the childcare centre. Therefore the
amount for liquidated damages was determined by the daily cost of the practices involvement in
administering the contract and providing observation beyond the set contract period. For a project
where the client has the potential to suffer a loss, practice policy is to send a liquidated damages pre-
assessment form to the client, to assist them in calculating their losses. This document allows
damages to be calculated at a set amount per calendar day, as most costs occur on this basis.
Tender Processes
The process for obtaining tenders can be carried out in different manners.
\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
32
Open tender –
This tender type is often undertaken by the public sector, where it is required to allow any interested
party to submit a tender. An invitation to tender is called by public advertisement (e.g. in major
newspapers or on websites such as GETS – Government Electronic Tenders Services) to ensure all
potential candidates have the opportunity to submit a price. This tender type will often require
tenderers to provide a deposit (to cover the cost or re-tendering if a tenderer withdraws his tender or
fails to sign a contract.
Advantages:
Gives emerging parties the chance to tender a project they might have otherwise missed.
Removes the liability of selecting tenderers from public servants.
Disadvantages:
Not all tenders received could be from parties with the experience or resources to
successfully carry out the contract works.
If a large number of tenders are received, there is considerable time spent in analysing so
many prices.
Selective tender –
This is the most common tender procurement process as the practice has good working relationships
with a range of contractors specialising in projects from residential to commercial scales.
Advantages:
Limits the number of received tenderers, so evaluating tenders can be faster.
Tenderers are selected based on their suitability to undertake the project, based on past
experience on projects of a similar size and nature.
Disadvantages:
Tenderers may be tempted to include the lowest subcontractor prices in their tender,
regardless of their experience or track record, simply to win the job. The risk of a
subcontractor’s performance then falls on the main contractor.
Negotiation –
This process can be suited to larger projects with a quantity surveyor on the project team. A selected
contractor becomes part of the team at an early stage (at which point the contractor’s preliminary and
general costs and margins are negotiated).
Advantages:
Project documentation can be produced in stages to save time.
Removes the potentially adversarial relationship between the architect and contractor.
No need for tender drawings – drawings can be produced solely for Building Consent and
construction purposes.
Disadvantages:
QS is responsible for ensuring that the contractor’s preliminaries and general costs are fair.
Lack of competitive bidding for main contractor’s works.
Selection of Tenderers
Our director and the client had a conversation about which tenderers to select. Some clients may
have builders in mind they want to have on the tender list. However, the client had no tenderers in
mind and confirmed he was happy to use those suggested by us. In the office we talked about
possible candidates, based on successful past collaborations and proven experience. A list of four
reputable prospective tenderers was compiled (appendix 21):
ABC Construction
DEF Construction
HIJ Interiors
LMN Construction
\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
33
Once the client had approved the list, the contractors were contacted and invited to tender. Tender
packages of full architectural and engineering drawings, specifications and SCC 2007 schedules
(appendix 22) along with a formal invitation letter, were couriered out on 5/10/09 and were due to be
submitted by 4.00pm on 28/10/09. Each tenderer received two full document sets in hard copy format
and a CD set of drawings. Our director wrote to the client confirming the call for tenders and they also
received a full set of tender documents for their records (appendix 23). I called tenderers the
following day to ensure they had received the documents.
During the tender period, I was the principal contact for tender enquiries. I also issued Notices to
Tenderers when required (which our director signed as a registered architect). An example where a
Notice was needed was an amendment to the project documentation regarding the amount of LPG
cylinders on site (appendix 24). To avoid delaying the processing of the Building Consent, the
number of gas cylinders on site had to be reduced from four to two, meaning that a small electric
water cylinder would be required to provide additional hot water to the nappy change room while the
rest of the building’s hot water would be from a Rinnai unit. In total, there were two Notices to
Tenderers couriered out and these were required to be acknowledged by all the tenderers in their
submissions, as proof of receipt.
Tender Evaluation
I called each tenderer a few days prior to tenders closing, to confirm they were on target to submit a
price on time. All four tenders were received by fax within the specified tender validly period, with
originals delivered to our office the next day.
I entered the tender information into an Excel spreadsheet that followed the layout of the trade
summary included in the tender package. None of the tenderers followed the trade summary
perfectly and there were some items that were included as part of other trades. However, the
spreadsheet allowed for easy comparison of prices and highlighted potential omissions or mistakes in
the tenders. Day rates, tags, margins and variation processing rates were also listed and compared.
Once the contingency sum and a sum for street services connections were included, three of the
tenders were below the latest QS estimate of $665,856.00 excluding GST. This meant that the
funding obtained by the client would be adequate. However, only two tenderers made reference to
programme – LMN Construction confirmed they could start construction 5 working days after Building
Consent was uplifted and DEF Construction noted that the contract period would need to be
discussed.
HIJ Interiors tender was the lowest. However, we noted the low amount in HIJ’s price for site works
(which also included drainage and excavation) compared to other prices received and were
concerned that this might be an error. When an architect spots a possible error in a tender, the
tenderer must be given the opportunity to review their price. They can either stand by it or
acknowledge a mistake and withdraw from the tendering process.
HIJ was given the chance to review their price for a possible mistake – a Tender Clarification asked
them to confirm their site works price and clarify several other points in their tender. HIJ stood by their
original site works price. Tender Clarifications were also sent to LMN and DEF (appendix 25). Once
we had received replies to the Clarifications, I was able to update the figures in the comparison
spreadsheet (appendix 26) and better compare the tenders.
I was still very concerned about HIJ’s comparatively low price for site works, excavation and drainage,
and what it could mean for the quality of the work if it were accepted. I also wondered whether this
price could cause problems during construction – if a mistake had indeed been made in the pricing,
the contractor may seek to recover losses through pricing variations in a less efficient manner and
cutting corners on site.
On the other hand, LMN’s tender was free of tags, they had the advantage of being based very close
to the project site and they had confirmed they could start on site promptly and commit to the
proposed programme. We were impressed with the quality and thoroughness of their tender, which
included a preliminary programme and information on company quality assurance procedures and
health and safety. We therefore decided that LMN were the best choice for the project.
\\Server\nzrab\2011\Registration 2011\Exemplars for website\Single document for
case study written commentary examples FINAL PM 2 FEB 2011.doc
34
Our director reported to the client, summarising the tender results and explaining why we believed
that LMN were the best choice for the contract even though their price was not the lowest (appendix
27). The final decision on which tender to accept is always the client’s. Once we received the client’s
acceptance of our recommendations, we wrote to LMN Construction on the client’s behalf to confirm
their tender was successful. I also then wrote to the other three tenderers, informing them of their
unsuccessful tenderers (appendix 28).
Minimising Risk
Regardless of what procurement method is used, it needs to be discussed early on with the
client, to make sure the client understands what arrangement would best suit their project.
The client also needs time to review the proposed contract to make sure they understand
contractual relationships and legal requirements.
If a client wants a project to be run under their own special contract, inform your Professional
Indemnity insurer. The contract also needs to be reviewed by your lawyer, so make the client
aware that there will be a cost involved for your lawyer's time.
Try to minimise the amount of monetary allowances in a contract – they represent cost
uncertainty to the client.
Keep Notices to Tenderers to a minimum and give the tenderers sufficient time to act on the
new information.
Make it clear to the client that the lowest tender is not necessarily the best tender and that
they are not obliged to accept any tenders.
If liquidated damages are to be written into the contract, assist the client in making an
assessment of the costs they believe they may incur if completion of the contract works is
late. Record the agreement in writing.
Tenderers can be invited to collect the tender documents from the office, rather than having
the documents sent to them. This gives the architect the opportunity to brief the tenderer on
the project and leave them with a clearer understanding before they start pricing.
Always remain fair and confidential to all involved parties during the tender process. All
tenderers should receive identical information.
When a tender is received, ensure that the time and date of receipt are clearly recorded. Late
tenders should be returned without analysis.